1. View | Gantt and set the Filter to "Critical" to see just critical path tasks.
2. View | Tracking Gantt will show all tasks with Critical Path tasks shown in red on the Gantt chart. Again, you can set the filter to "Critical" if you want to see just those tasks.
You might also want to look at Tools | Options | Calculation-tab to adjust the amount of slack from 0 to perhaps 1 or 2 so that tasks with only a day or two of slack will also be shown as critical.
Member for
20 years 4 monthsRE: Critical Path and Rescheduling
L.E.N thanks for good options
Member for
18 years 3 monthsRE: Critical Path and Rescheduling
You have several choices:
1. View | Gantt and set the Filter to "Critical" to see just critical path tasks.
2. View | Tracking Gantt will show all tasks with Critical Path tasks shown in red on the Gantt chart. Again, you can set the filter to "Critical" if you want to see just those tasks.
You might also want to look at Tools | Options | Calculation-tab to adjust the amount of slack from 0 to perhaps 1 or 2 so that tasks with only a day or two of slack will also be shown as critical.
Member for
20 years 4 monthsRE: Critical Path and Rescheduling
Thanks Briole
Member for
22 years 9 monthsRE: Critical Path and Rescheduling
Hello,
the easiest way to display the critical path in MS Project Gantt chart is to use Format, Gantt chart wizard.
hth,
Alexandre