Exporting WBS code from P3 to MSP

Member for

22 years 9 months

Jaya,

WBS code is entirely different in P3 and MSP:

in P3, you create a WBS structure, and apply the structure to all the activities which belong to a particular branch;

in MSP, each and every is using its own wbs code.

I am aware of two different ways to retrieve P3 WBS structure in MSP:

a. Use the "Utils P3" MS Excel files available on Primavera web site,

b. create a customized wbs code in MSP Project, WBS Code, Define, and use your P3 WBS structure as a template.

Good luck,

Alexandre