I did extensive testing when writing my Primavera Enterprise book and it worked with my system.
I have also just checked again and I can confirm a LOE may work the same as a Hammock but may also work differently depending on the relationships used.
A Hammock in P3 and SureTrak will only span from the Start of one or more activities to the Finish of one or more, and therefore spans a period when work takes place.
IN PE a LOE will span from the finish of activities to the start of activities which was not possible with P3 & SureTrak. Therefore may span a period when there are not activities scheduled.
Thanks, I know this one already. According to manual "Move P3 to P3e/c", if more than one predeccessor and succesor assigned, the ES of LOE is latest ES dates and EF of LOE is earliest LF dates.
I do some tests on P3e/c v3.5, cannot work out what described in manual, the result always same as hommack, ie ES of LOE is earliest ES dates and EF of LOE is latest EF dates.
Member for
23 years 8 monthsRE: Level of Effort Activity Type
Thanks. Ill do some more test, especially the combination on relationship type.
Member for
24 years 7 monthsRE: Level of Effort Activity Type
I did extensive testing when writing my Primavera Enterprise book and it worked with my system.
I have also just checked again and I can confirm a LOE may work the same as a Hammock but may also work differently depending on the relationships used.
Paul E Harris
Eastwood Harris Pty Ltd
Planning and Scheduling Book Publishers
www.eh.com.au
Member for
23 years 8 monthsRE: Level of Effort Activity Type
I cannot work out the span from the finish of activities to the start of activities for a LOE in P3e/c!! I dont know why.
It always behave a hommack as P3
Member for
24 years 7 monthsRE: Level of Effort Activity Type
A Hammock in P3 and SureTrak will only span from the Start of one or more activities to the Finish of one or more, and therefore spans a period when work takes place.
IN PE a LOE will span from the finish of activities to the start of activities which was not possible with P3 & SureTrak. Therefore may span a period when there are not activities scheduled.
I hope this clarifies things.
Paul E Harris
Eastwood Harris Pty Ltd
Planning and Scheduling Book Publishers
www.eh.com.au
Member for
23 years 8 monthsRE: Level of Effort Activity Type
Thanks, I know this one already. According to manual "Move P3 to P3e/c", if more than one predeccessor and succesor assigned, the ES of LOE is latest ES dates and EF of LOE is earliest LF dates.
I do some tests on P3e/c v3.5, cannot work out what described in manual, the result always same as hommack, ie ES of LOE is earliest ES dates and EF of LOE is latest EF dates.
Am I miss anything any setting?