Level of Effort Activity Type

Member for

23 years 8 months

Thanks. I’ll do some more test, especially the combination on relationship type.

Member for

24 years 7 months

I did extensive testing when writing my Primavera Enterprise book and it worked with my system.



I have also just checked again and I can confirm a LOE may work the same as a Hammock but may also work differently depending on the relationships used.



Paul E Harris

Eastwood Harris Pty Ltd

Planning and Scheduling Book Publishers

www.eh.com.au

Member for

23 years 8 months

I cannot work out the span from the finish of activities to the start of activities for a LOE in P3e/c!! I don’t know why.

It always behave a hommack as P3

Member for

24 years 7 months

A Hammock in P3 and SureTrak will only span from the Start of one or more activities to the Finish of one or more, and therefore spans a period when work takes place.



IN PE a LOE will span from the finish of activities to the start of activities which was not possible with P3 & SureTrak. Therefore may span a period when there are not activities scheduled.



I hope this clarifies things.



Paul E Harris

Eastwood Harris Pty Ltd

Planning and Scheduling Book Publishers

www.eh.com.au

Member for

23 years 8 months

Thanks, I know this one already. According to manual "Move P3 to P3e/c", if more than one predeccessor and succesor assigned, the ES of LOE is latest ES dates and EF of LOE is earliest LF dates.



I do some tests on P3e/c v3.5, cannot work out what described in manual, the result always same as hommack, ie ES of LOE is earliest ES dates and EF of LOE is latest EF dates.



Am I miss anything any setting?