You can also use Copy Ctrl-C then Paste Ctrl-V then using auto increment change the values of your ids. If the scope of work is repetitive, you can link and load them with resources before copying. That way, when you begin pasting those activities you only need to link the floors. That will also depends on your programmed work cycles.
1. Create a typical cycle for each floor, if u r doing building project, or may be for one particular section, if u doing road / pipeline project. Use only 7 digits for ACTIVITY ID.
2. Link all these activities using appropriate lags with levels assigned to it.
Once this typical cycle is over, then filter NO ACTIVITIES, paste this typcial cycle, and then change the prefix for each floor.
EXAMPLE: (For the project, i m working into)
THERE CAN BE ONLY 10 DIGIT ACTIVITY ID
Lets split that into following for say Building project:
- First 3 digit for each floor. Create Code list for same.
- 1 digit for space, say tower, podium, pool, annex etc.
- 2 digits for specification - type of work involved like concrete, masonary, wood, metal, pre-construction etc.
- 3 digit for the particular activity
- 1 digit for revision
Now create a typical cycle for say structural works and interior fit-out works. Assign them only last seven digits and then paste this cycle every time with required prefix of floor. THIS IS WHAT YOU ASKED, RIGHT?
And the only work now balance is linking floor to floor activities.
THE END :-)
Cheers,
Raviraj
Member for
19 years 9 months
Member for19 years10 months
Submitted by Haris Famil Parol on Tue, 2007-10-02 15:39
what Paul has said in first is a very nice option.
i always prefer that.
i would like to share something which i have learned.
that in p3 we have activity id limitations upto 10 characters. so even if we activity id of only one character, p3 saves the activity id as 9 blanks and 1 character, so if you want to amend that activity and add somthing into the prefix or suffix, first u will have to remove those blanks and then give the numbering u want.
now this is my assumption.
I would be grateful if our senior planners could just guide me on this, whether i am right or wrong.
Member for
18 years 5 monthsRE: Change Activity ID in p3
Thats true,
Oops!! I forget to say that
Member for
20 years 3 monthsRE: Change Activity ID in p3
Hi Raviraj,
You can also use Copy Ctrl-C then Paste Ctrl-V then using auto increment change the values of your ids. If the scope of work is repetitive, you can link and load them with resources before copying. That way, when you begin pasting those activities you only need to link the floors. That will also depends on your programmed work cycles.
Regards,
Ed
Member for
18 years 5 monthsRE: Change Activity ID in p3
Theres one more easy way to do this.
1. Create a typical cycle for each floor, if u r doing building project, or may be for one particular section, if u doing road / pipeline project. Use only 7 digits for ACTIVITY ID.
2. Link all these activities using appropriate lags with levels assigned to it.
Once this typical cycle is over, then filter NO ACTIVITIES, paste this typcial cycle, and then change the prefix for each floor.
EXAMPLE: (For the project, i m working into)
THERE CAN BE ONLY 10 DIGIT ACTIVITY ID
Lets split that into following for say Building project:
- First 3 digit for each floor. Create Code list for same.
- 1 digit for space, say tower, podium, pool, annex etc.
- 2 digits for specification - type of work involved like concrete, masonary, wood, metal, pre-construction etc.
- 3 digit for the particular activity
- 1 digit for revision
Now create a typical cycle for say structural works and interior fit-out works. Assign them only last seven digits and then paste this cycle every time with required prefix of floor. THIS IS WHAT YOU ASKED, RIGHT?
And the only work now balance is linking floor to floor activities.
THE END :-)
Cheers,
Raviraj
Member for
19 years 9 monthsRE: Change Activity ID in p3
- First create a new Activity Code (NewID) = 10 Char
- Export ID, Name and NewId
- Create a new ID in NewID (in Excel)
- Import
- use Global Change to replace ID with NewID
Regards
Hannes de Bruyne
05 Sep 2007, 08:11 #4
Mangesh Khuspe
Building Works
Member since Apr 2007
United Arab Emirates (AS.AE)
this one works well, thank u sir :)
--------------------------------------------------------------------------------
Hi
ASHKAN KHALESI
the best thing i have found is to make some changes in p3.ini file.
go to help menu-->search p3.ini--->customize settings-->
in this file u will find all that u want.
cheers
mangesh
thi .ini file helps for few other action like makin a project exclusive wen there no option to do so
thank u all, u made mah day :)
Member for
18 years 6 monthsRE: Change Activity ID in p3
hi
Ashkan
what Paul has said in first is a very nice option.
i always prefer that.
i would like to share something which i have learned.
that in p3 we have activity id limitations upto 10 characters. so even if we activity id of only one character, p3 saves the activity id as 9 blanks and 1 character, so if you want to amend that activity and add somthing into the prefix or suffix, first u will have to remove those blanks and then give the numbering u want.
now this is my assumption.
I would be grateful if our senior planners could just guide me on this, whether i am right or wrong.
cheers
Mangesh
Member for
24 years 6 monthsRE: Change Activity ID in p3
After backing up your project, your can either:
1. Copy all the activities and then paste them selecting an appropriate renumbering method, then delete the original activities.
2. Use a Global Change.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Member for
20 years 3 monthsRE: Change Activity ID in p3
- First create a new Activity Code (NewID) = 10 Char
- Export ID, Name and NewId
- Create a new ID in NewID (in Excel)
- Import
- use Global Change to replace ID with NewID
Regards
Hannes de Bruyne
Member for
18 years 6 monthsRE: Change Activity ID in p3
Hi
ASHKAN KHALESI
the best thing i have found is to make some changes in p3.ini file.
go to help menu-->search p3.ini--->customize settings-->
in this file u will find all that u want.
cheers
mangesh
Member for
18 years 9 monthsRE: Change Activity ID in p3
Mark "Exclusive" before you open the project. Then you can modify the ids
Dieter