changed the WBS :locate activities with old WBS values

Member for

18 years 9 months

thanks ferdinand and oliver , that were excellent ideas.

now while in my wbs layout (with all activities filter) there are 1527 activties , where as when i sort by project i get 1531 activities , i dotn know where the 4 activities go in wbs layout.

regards

deb

Member for

23 years

In your WBS view, use a spare Activity Code field as a column, and fill this with a value.



Switch to activity view, and with the same column diplayed. Any activity which does not have an entry in the Activity Code field doesnt match the WBS ( I Think !)