Resource Loading !

Member for

19 years 9 months

Thnx Deepak...I agree with you on requirement of 9 Men days but in the current situation , it’s the same resource & thus 3 men can work every day for 3 days to equate to 9 Men Days in total. So, I need 3 men to complete the activity NOT 9 as defined by P3



Thnx Raviraj...but i don’t think that it’s an issue related to Report Writing/ID etc. The problem I could imagine is because in P3 , Budgeted Quantity (BQ) = (Units/Day x Activity Duration) . This linear equation doesn’t incorporate any variable for Concurrent/Repetitive units

Member for

18 years 5 months

VERY Interesting....



Shud not happen actually.



As Datta has said, u must hav used single resource.



Better way wud b, go to TOOLS --> GRAPHIC REPORTS --> RESOURCE AND COST



Add one more ID into it



and then produce the Histogram / Curve required.



Remember to change items in following tabs at least:



Resource Selection

Content

Date

Selection



If there is still problem, plz revert back.



Cheers,



Raviraj

Member for

22 years 6 months

Dear Deepak,

If the trades are different, then use different resources.

If they are doing same work, use a same resource (Welder etc)

You require 9 mandays to do the work, with 3 no of resources, you will take 3 days.

Unless you have a different plan for these people thruout the rest of the project, you can always combine the resources. & also think about the type of reports u want to generate & then decide.



Cheers

Deepak

Member for

22 years 6 months

Dear Deepak,

If the trades are different, then use different resources.

If they are doing same work, use a same resource (Welder etc)

You require 9 mandays to do the work, with 3 no of resources, you will take 3 days.

Unless you have a different plan for these people thruout the rest of the project, you can always combine the resources. & also think about the type of reports u want to generate & then decide.



Cheers

Deepak