Have you assigned any resource to this activity or these activities? Check the availability of the assigned resources in resource dictionary.

Member for

23 years 9 months

Hi,



Constraining an activity is Conditioned..it is not just constrain whatever..



Contraining Can’t be more or less than the early & Late dates that have been calculated by CPM.



ex.If you want constrain Late Finish date..you can but the constrain and it will work If and Only If the constrain date is Less than the Late Finish date(CPM calculation).If the Constrain date is More than the Late finish date,the constrain will not work..and it will take the Original Late Finish date Instead..and so on with other constrains.



check out the constraint dates links..may be this is the problm..



I hope this will help