Job Cards from Plan

Member for

21 years 5 months

On a previous project I exported the activity data with a "1-week look-ahead filter" to Excel/Access. From there on you can add fields for actual ressources/manhours used, delays encountered etc. By using Access reports your printing possibilities are virtually unlimited.

The intrinsic advantage of the jobcards of course is the organized and disciplined progress reporting (once you have educated the individuals involved!)

In addition you end up with a database containing all the project history linked to the Primavera activities. The forensic schedulers loved it!



Cheers, Marcel

Member for

19 years 1 month

i guess yes, but that would depend on the tasks, i.e. descriptions and durations; maybe you need your job cards daily, then you’ll need lots of details as well