Markup on quotation

Member for

22 years 4 months

Apparently you can’t claim this mark up separately as this is already included in your profit and overheads on the said item. Further you need to seek contractual provisions as well as Tender documents to clear on that issue

Member for

19 years

I think your contract document shall have specified what your mark up shall include. Please check.

Member for

19 years 2 months



Dear All

in my opinion,this markup for attendance,storage,transportation including overhead and profit .

you are not allowed to claim for any thing more.

Member for

19 years 2 months



Dear All

in my opinion,this markup for attendance,storage,transportation including overhead and profit .

you are not allowed to claim for any thing more.

Member for

19 years 2 months



Dear All

in my opinion,this markup for attendance,storage,transportation including overhead and profit .

you are not allowed to claim for any thing more.

Member for

19 years 2 months



Dear All

in my opinion,this markup for attendance,storage,transportation including overhead and profit .

you are not allowed to claim for any thing more.

Member for

19 years 2 months



Dear All

in my opinion,this markup for attendance,storage,transportation including overhead and profit .

you are not allowed to claim for any thing more.

Member for

19 years 2 months



Dear All

in my opinion,this markup for attendance,storage,transportation including overhead and profit .

you are not allowed to claim for any thing more.

Member for

18 years 6 months

Hello Sermet,



It is a mark-up on procurement of material for variations calculation. Your appendix must have the manhour rates and the equipment rates.



Hernan

Member for

18 years 6 months

Hi,



As per my experience this mark-up is to cover the cost of procurement effort which the contractor spend on ordering.



Once the equipmet/material is delivered to site, the cost incurred in warehousing and storage etc are part of Construction and not procurement so you must charge for it.





Regards,



Ashraf

Member for

18 years 5 months



Dear Serment,



What form of contract are u operating?