S curve generation

Member for

20 years 2 months

Hi anoon,



I wish you dont feel cold nowadays.. Will it be harmfull to use total? I dont have any ideas, maybe you can help me .

Member for

19 years 1 month

don’t use total, use average and peak

Member for

20 years 2 months

I will try to answer your question eventhough your question is not well clear to me.

You are able to use any of the three option you may wish to suit your project requirement. You need to generate your S- to track your project, if my assumption is right then 1st you need a baseline to be able for you to compare with current status.

Member for

22 years 6 months

Hi Ulysses,



Thanks.



The problem is how get the weekly or monthly distribution for S curve generation.



Usually I use CL-03 Tabular Cost Loading report. When you go to CL-03----> modify ----> time scale ---> there are 3 usages i.e. Avg, peak and total - my 1st question is which one to use to get monthly or weekly distribution? I usally use Total --- is that correct way to do.



Usually how to get (means procedure) monthly or weekly distribution for S curve generation?



Kindly provide your feedback.

Member for

20 years 2 months

will you please make your question straight forward. maybe i could be of help