Primavera Project Planner - P3 Member for 21 years 10 months Member for 21 years 10 months Submitted by moutaz aldeib on Sat, 2007-06-02 10:00 Permalink RE: Activity Description Thanks Ashraf, It is working. Member for 18 years 6 months Member for 18 years 6 months Submitted by Ashraf Jahangeer on Sat, 2007-06-02 04:29 Permalink RE: Activity Description Insert as many activities as you like leaving the description blank. Select the activity description including the one you want to copy. Right click the mouse and press fill cell. Regards, Ashraf Log in or register to post comments
Member for 21 years 10 months Member for 21 years 10 months Submitted by moutaz aldeib on Sat, 2007-06-02 10:00 Permalink RE: Activity Description Thanks Ashraf, It is working.
Member for 18 years 6 months Member for 18 years 6 months Submitted by Ashraf Jahangeer on Sat, 2007-06-02 04:29 Permalink RE: Activity Description Insert as many activities as you like leaving the description blank. Select the activity description including the one you want to copy. Right click the mouse and press fill cell. Regards, Ashraf
Member for
21 years 10 monthsRE: Activity Description
Thanks Ashraf,
It is working.
Member for
18 years 6 monthsRE: Activity Description
Insert as many activities as you like leaving the description blank.
Select the activity description including the one you want to copy. Right click the mouse and press fill cell.
Regards,
Ashraf