Primavera Project Planner - P3 Member for 22 years 5 months Member for 22 years 5 months Submitted by Zq qz on Sun, 2004-01-18 23:44 Permalink RE: rebaseline Another method is using your current schedule as your target Member for 21 years 10 months Member for 21 years 10 months Submitted by Bensouyah Mohamed on Sun, 2004-01-18 12:43 Permalink RE: rebaseline next time i’ll give u a real example of project Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sat, 2004-01-17 09:48 Permalink RE: rebaseline Make use fields, like custom data fields, to store some calculated values in step by step calculation. The whole process is control by global change. Member for 22 years 5 months Member for 22 years 5 months Submitted by Zq qz on Sat, 2004-01-17 05:31 Permalink RE: rebaseline Another method is Update Target Option Member for 16 years 9 months Member for 16 years 9 months Submitted by PPAdmin on Fri, 2004-01-16 10:34 Permalink RE: rebaseline please more explications Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Thu, 2004-01-15 21:20 Permalink RE: rebaseline by global change to update the required field(s). Log in or register to post comments
Member for 22 years 5 months Member for 22 years 5 months Submitted by Zq qz on Sun, 2004-01-18 23:44 Permalink RE: rebaseline Another method is using your current schedule as your target
Member for 21 years 10 months Member for 21 years 10 months Submitted by Bensouyah Mohamed on Sun, 2004-01-18 12:43 Permalink RE: rebaseline next time i’ll give u a real example of project
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sat, 2004-01-17 09:48 Permalink RE: rebaseline Make use fields, like custom data fields, to store some calculated values in step by step calculation. The whole process is control by global change.
Member for 22 years 5 months Member for 22 years 5 months Submitted by Zq qz on Sat, 2004-01-17 05:31 Permalink RE: rebaseline Another method is Update Target Option
Member for 16 years 9 months Member for 16 years 9 months Submitted by PPAdmin on Fri, 2004-01-16 10:34 Permalink RE: rebaseline please more explications
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Thu, 2004-01-15 21:20 Permalink RE: rebaseline by global change to update the required field(s).
Member for
22 years 5 monthsRE: rebaseline
Another method is using your current schedule as your target
Member for
21 years 10 monthsRE: rebaseline
next time i’ll give u a real example of project
Member for
23 years 8 monthsRE: rebaseline
Make use fields, like custom data fields, to store some calculated values in step by step calculation.
The whole process is control by global change.
Member for
22 years 5 monthsRE: rebaseline
Another method is Update Target Option
Member for
16 years 9 monthsRE: rebaseline
please more explications
Member for
23 years 8 monthsRE: rebaseline
by global change to update the required field(s).