Oracle Primavera - PM6 Member for 19 years 3 months Member for 19 years 3 months Submitted by Arthur Godbeer on Thu, 2007-05-24 08:24 Permalink RE: limited licensed activities in p3 contractor If youre asking about limitations on the number of activities in Contractor, then by design Standard is a max of 750 per project and Deluxe is 2000. Project Management in the Planner/Scheduler s/w is unlimited. Log in or register to post comments
Member for 19 years 3 months Member for 19 years 3 months Submitted by Arthur Godbeer on Thu, 2007-05-24 08:24 Permalink RE: limited licensed activities in p3 contractor If youre asking about limitations on the number of activities in Contractor, then by design Standard is a max of 750 per project and Deluxe is 2000. Project Management in the Planner/Scheduler s/w is unlimited.
Member for
19 years 3 monthsRE: limited licensed activities in p3 contractor
If youre asking about limitations on the number of activities in Contractor, then by design Standard is a max of 750 per project and Deluxe is 2000. Project Management in the Planner/Scheduler s/w is unlimited.