P3e basics

Member for

20 years

Go on group & sort / sort by ... or just click on header column.



Regards.

Member for

19 years

mh shaw,



If your activity sequence is by activity ID just click the headers of activity ID and it will sort by activity Id or click any headers that correspond to your original sequence such as start, finish...etc



If you’re not happy on the result, use group & sort to organise your activities.



Hope this help.



Rodel