Baseline

Member for

18 years 6 months

Marcio ,





at the time you set your currnt project as a Baseline as you mentioned

your planned start = Base line start

Planned Finish = Base line finish which is correct untill your first update of the schedule



also



as you prgress they will change ,



They are couple of good query regarding baseline i suggest ou review them,





Regards,



Hamed

Member for

21 years

Was there any progress in your project when you made the first baseline?