1. Activity Durations: You may want to do a global change to divide all durations by 8 to convert from hourly durations to days. Or you may want to export Act ID and OD to excel, divide all ODs by 8, and import back into P3.
2. MS Project uses sub-activities to handle WBS. Primavera handles it differently. Since youre moving to P3, you have to decide if youre going to use Activity Coding and/or WBS. In any case, you may delete these topic activities from MSP. But youll have to create a project structure (Act Coding or WBS) to categorize your detailed activities.
This is what I meant by "doing some work" when converting from MSP to P3. Its never a straighforward thing. One time I converted a small schedule from MSP to P3 and it took me a loooong time. I should have just done it in P3 from scratch instead of importing the schedule.
Goodluck.
Jorge
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Thu, 2007-04-26 03:51
1. Topic activities are specific to SureTrak; they "summarize informations about the activities that are subordinate to it", they have no duration of their own, their duration is the elapsed time between the start of the 1st of their subordiante activities and the end of their last subordinate activities, i.e. they are very closed to hammock activities, the main difefrence being that a hammock is created by the user and a topic by the software.
2. I have just tried once again to convert a small mpp file with duration in days to mpx to p3 (by using sciforma mpx2000 utilitiy) and my p3 plan is well in days.
Alexandre
Member for
18 years 7 months
Member for18 years7 months
Submitted by DURGESH NARAYA… on Wed, 2007-04-25 08:10
i just converted msp programme in to mpx to convert in p3,
the problem i am facing is that, earlier the duration of the activities were in days & now they have automatically converted in hours in mpx programme which i want to be in days.
2nd problem is thatwhn i am conVerting mpx programme in p3, the main task is coming as TOPIC & NOT AS HAMMOK.HOW TO CHANGE IT AS HAMMOK ACTIVITY TYPE.
IF ANY BODY CAN HELP IN THAT.
THNX & REGARDS
DURGESH MISHRA
SIEMENS-ETA CONSORTIUM
Member for
18 years 7 months
Member for18 years7 months
Submitted by DURGESH NARAYA… on Wed, 2007-04-25 08:09
i just converted msp programme in to mpx to convert in p3,
the problem i am facing is that, earlier the duration of the activities were in days & now they have automatically converted in hours in mpx programme which i want to be in days.
2nd problem is thatwhn i am conerting mpx programme in p3, the main task is coming as TOPIC & NOT AS HAMMOK.
IF ANY BODY CAN HELP IN THAT.
THNX & REGARDS
DURGESH MISHRA
SIEMENS-ETA CONSORTIUM
Member for
22 years 4 months
Member for22 years4 months
Submitted by Jorge Taguinod on Mon, 2007-04-16 02:15
Hello Jorge, There are two import utilities, You make use of activity.xls. There is also dictionary.xls. With this tool you can indeed fill WBS and also Resources, Custom data items,Cost account information. Regards.
Member for
22 years 4 months
Member for22 years4 months
Submitted by Jorge Taguinod on Sun, 2007-04-15 21:28
P3s import facility can only be used to import activity data. You cant use this facility to modify dictionaries (e.g. WBS structure). To do this, you will need to either input it manually in P3 or use Batch Processing.
Please refer to the documentation included in your software for this.
Note: Its quite difficult to use WBS in P3, but its a breeze in MSP and P3e. This is the reason youre having quite a hard time importing from MSP. The technical process is easy. Its the rework thats a pain. Consider using P3e.
If I remember correctly P3 imports the WBS codes but not descriptions.
On the Primavera webs site Solution ID: 200252492644 supplies an Excel spreadsheet that can be used import the WBS codes and descriptions from MSP to P3.
You should be able to copy & paste the MSP WBS codes and summary task descriptions from MSP to the Excel Spreadsheet and then upload them to P3.
I have not specifically done this operation myself, but I often import Activity Code and Activity ID descriptions. If I had many WBS descriptions to upload, then this would be my approach.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
You can fill a text field in MSP with the value of your WBS before you convert, and during conversion it can be made an Activity code. After that you can make the WBS equal to the Activity code you created with a global change.
Regards Alphons
Member for
18 years 7 months
Member for18 years7 months
Submitted by DURGESH NARAYA… on Sun, 2007-04-08 05:34
Please, kindly do me favor pls. I have tried all the instructions from you on this site. Thanks a lot. But since I tried to download this MPPtoMPX.exe from Primavera site, I can not register my P3 software, because its said my software is old in version, although my software is licensed officially ordered from Primavera itself by my company. Pls. kindly suggest how to solve the problem with convertion of MS Project 2000 files to P3. It is extremely important for me. May someone can forward me MPPtoMPX.exe utility already downloaded or there is another clue? My e-mail address guseinm@hotmail.com , corporate GMamedov@mqs.az
I still suggest to re-do the import, then use some tools, like ClaimsDigger, PrimaPlan Project Investigator, etc to compare the 2 projects to list the differences. Then input those difference to the new one. I assume the difference are major your previous effort.
Member for
21 years 10 months
Member for21 years11 months
Submitted by Clive Hibberd on Fri, 2004-01-23 10:51
Can anyone help? I have converted a MS Project 2000 programme to P3 but forgot to outdent all the activities before converting. The result is that now I keep getting Topic activities showing in P3 but cant change them. If I create new tasks to replace the topic activities, and then delete the topic activities, P3 then changes the activity above from a task to a topic activity. Does anyone have a fix for this? Unfortunately I cant re-do the import conversion because I have made many changes to the programme since.
Member for
23 years 4 months
Member for23 years4 months
Submitted by Dave Rodwell on Mon, 2003-11-24 12:04
I have tackled this conversion many times. It is not too bad to do, just make a cup of coffe, get comfortaable and allow sufficient time without interruption.
Member for
22 years 4 months
Member for22 years4 months
Submitted by Jorge Taguinod on Mon, 2003-11-24 11:32
This is going to be difficult especially of you want to be organized about it. One of your major problem would be activity coding, expecially if you need to convert multiple MSP schedules into a P3 project group.
I anticipate that you would have problems with most if not all the items under the Data Menu.
Member for
22 years 4 monthsRE: Microsoft Project conversion to P3 expectation
Durgesh,
1. Activity Durations: You may want to do a global change to divide all durations by 8 to convert from hourly durations to days. Or you may want to export Act ID and OD to excel, divide all ODs by 8, and import back into P3.
2. MS Project uses sub-activities to handle WBS. Primavera handles it differently. Since youre moving to P3, you have to decide if youre going to use Activity Coding and/or WBS. In any case, you may delete these topic activities from MSP. But youll have to create a project structure (Act Coding or WBS) to categorize your detailed activities.
This is what I meant by "doing some work" when converting from MSP to P3. Its never a straighforward thing. One time I converted a small schedule from MSP to P3 and it took me a loooong time. I should have just done it in P3 from scratch instead of importing the schedule.
Goodluck.
Jorge
Member for
22 years 9 monthsRE: Microsoft Project conversion to P3 expectation
Durgesh,
1. Topic activities are specific to SureTrak; they "summarize informations about the activities that are subordinate to it", they have no duration of their own, their duration is the elapsed time between the start of the 1st of their subordiante activities and the end of their last subordinate activities, i.e. they are very closed to hammock activities, the main difefrence being that a hammock is created by the user and a topic by the software.
2. I have just tried once again to convert a small mpp file with duration in days to mpx to p3 (by using sciforma mpx2000 utilitiy) and my p3 plan is well in days.
Alexandre
Member for
18 years 7 monthsRE: Microsoft Project conversion to P3 expectation
hi all!
i just converted msp programme in to mpx to convert in p3,
the problem i am facing is that, earlier the duration of the activities were in days & now they have automatically converted in hours in mpx programme which i want to be in days.
2nd problem is thatwhn i am conVerting mpx programme in p3, the main task is coming as TOPIC & NOT AS HAMMOK.HOW TO CHANGE IT AS HAMMOK ACTIVITY TYPE.
IF ANY BODY CAN HELP IN THAT.
THNX & REGARDS
DURGESH MISHRA
SIEMENS-ETA CONSORTIUM
Member for
18 years 7 monthsRE: Microsoft Project conversion to P3 expectation
hi all!
i just converted msp programme in to mpx to convert in p3,
the problem i am facing is that, earlier the duration of the activities were in days & now they have automatically converted in hours in mpx programme which i want to be in days.
2nd problem is thatwhn i am conerting mpx programme in p3, the main task is coming as TOPIC & NOT AS HAMMOK.
IF ANY BODY CAN HELP IN THAT.
THNX & REGARDS
DURGESH MISHRA
SIEMENS-ETA CONSORTIUM
Member for
22 years 4 monthsRE: Microsoft Project conversion to P3 expectation
Hi Alphons,
I didnt know that. I use Batch File to do it. Thank you very much for the information. This should make things much easier.
Do you have the utility? Or can you tell me where to get it?
Cheers,
Jorge
Member for
23 years 9 monthsRE: Microsoft Project conversion to P3 expectation
Hello Jorge, There are two import utilities, You make use of activity.xls. There is also dictionary.xls. With this tool you can indeed fill WBS and also Resources, Custom data items,Cost account information. Regards.
Member for
22 years 4 monthsRE: Microsoft Project conversion to P3 expectation
P3s import facility can only be used to import activity data. You cant use this facility to modify dictionaries (e.g. WBS structure). To do this, you will need to either input it manually in P3 or use Batch Processing.
Please refer to the documentation included in your software for this.
Note: Its quite difficult to use WBS in P3, but its a breeze in MSP and P3e. This is the reason youre having quite a hard time importing from MSP. The technical process is easy. Its the rework thats a pain. Consider using P3e.
Jorge
Member for
24 years 6 monthsRE: Microsoft Project conversion to P3 expectation
If I remember correctly P3 imports the WBS codes but not descriptions.
On the Primavera webs site Solution ID: 200252492644 supplies an Excel spreadsheet that can be used import the WBS codes and descriptions from MSP to P3.
You should be able to copy & paste the MSP WBS codes and summary task descriptions from MSP to the Excel Spreadsheet and then upload them to P3.
I have not specifically done this operation myself, but I often import Activity Code and Activity ID descriptions. If I had many WBS descriptions to upload, then this would be my approach.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Member for
23 years 9 monthsRE: Microsoft Project conversion to P3 expectation
You can fill a text field in MSP with the value of your WBS before you convert, and during conversion it can be made an Activity code. After that you can make the WBS equal to the Activity code you created with a global change.
Regards Alphons
Member for
18 years 7 monthsRE: Microsoft Project conversion to P3 expectation
THNX!!
I CONVERTED MSP IN TO P3 BUT THE PROBLEM NOW I AM FACING IS THAT P3 IS NOT TAKING MSPS WBS DIRECTLY...
ANY SOLUTION ...PLZ.
THNANK YOU.
Member for
22 years 11 monthsRE: Microsoft Project conversion to P3 expectation
You can also try:
I would suggest you contact Primavera directly with any licensing issues you may be experiencing with their software.
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Member for
21 years 9 monthsRE: Microsoft Project conversion to P3 expectation
Dear All!
Please, kindly do me favor pls. I have tried all the instructions from you on this site. Thanks a lot. But since I tried to download this MPPtoMPX.exe from Primavera site, I can not register my P3 software, because its said my software is old in version, although my software is licensed officially ordered from Primavera itself by my company. Pls. kindly suggest how to solve the problem with convertion of MS Project 2000 files to P3. It is extremely important for me. May someone can forward me MPPtoMPX.exe utility already downloaded or there is another clue? My e-mail address guseinm@hotmail.com , corporate GMamedov@mqs.az
Member for
23 years 8 monthsRE: Microsoft Project conversion to P3 expectation
I still suggest to re-do the import, then use some tools, like ClaimsDigger, PrimaPlan Project Investigator, etc to compare the 2 projects to list the differences. Then input those difference to the new one. I assume the difference are major your previous effort.
Member for
21 years 10 monthsRE: Microsoft Project conversion to P3 expectation
Topic activities in P3
Can anyone help? I have converted a MS Project 2000 programme to P3 but forgot to outdent all the activities before converting. The result is that now I keep getting Topic activities showing in P3 but cant change them. If I create new tasks to replace the topic activities, and then delete the topic activities, P3 then changes the activity above from a task to a topic activity. Does anyone have a fix for this? Unfortunately I cant re-do the import conversion because I have made many changes to the programme since.
Member for
23 years 4 monthsRE: Microsoft Project conversion to P3 expectation
I have tackled this conversion many times. It is not too bad to do, just make a cup of coffe, get comfortaable and allow sufficient time without interruption.
Member for
22 years 4 monthsRE: Microsoft Project conversion to P3 expectation
Uh oh!
This is going to be difficult especially of you want to be organized about it. One of your major problem would be activity coding, expecially if you need to convert multiple MSP schedules into a P3 project group.
I anticipate that you would have problems with most if not all the items under the Data Menu.
Too long to expound here.
Jorge
Member for
24 years 6 monthsRE: Microsoft Project conversion to P3 expectation
There is a technical paper on my web site www.eh.com.au on converting P3/STW to and from MSP.
Regards
Paul E Harris