Activities NOT Leveled!

Member for

24 years 6 months

These are the sort of things that will stop leveling:



Have you selected a resource to level in the Level form? The resources to be leveled should selected in the Level form.

Have you set the Limits in the Resource Dictionary? A resource needs a limit to level.

A resource will not be leveled when you assigned a resource to an activity at a Units per time period greater than available in the resource dictionary. This may occur when:

– The Resource Limit in the Resource Dictionary is reduced, or

– A Task has been assigned a resource with a Unit per Time Period that is greater than the Limit, or

– When the Freeze Units per Time Period is unchecked and the duration of an activity has been reduced thus increasing the assigned Units per time period over the maximum available in the Resource form.

Have you assigned a Mandatory constraint to an unleveled task? Tasks with a Mandatory constraint will not be leveled.

Have you set Smoothing to Time constrained. This option may prevent activities without float from leveling.

Have you a Resource Group with the Hierarchical Resource and one or more resource within the group which have not be specified a limit? (which, therefore gives the group unlimited availability).

Have you a corrupt file?



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au


Member for

22 years 9 months

hashid,

do you have scheduling constraints on these activities?

Alexandre