To clarify my point, herebelow is a simple example.
Create a new project with planning unit in weeks, starting on mondays and with a start date of January 5th 2004.
Activity 1 has duration of 2 weeks and is linked with FS to Activity 2 that has a duration of 3 weeks.
The Bar Chart Layout shows Activity 1 finishing on January 18th 2004, and Activity 2 on February 8th, 2004, and both are correct.
Now, if you go to View, PERT, it shows Activity 1 finishing on January 12th 2004, and Activity 2 on February 2nd, 2004, and both are wrong. These 2 finish dates represent the starting dates of the weeks in which these activities end.
Member for
22 years 3 monthsRE: Bar Chart & Network (PERT) Finish Dates not Ma
I just try it on my P3 and there are not any discrepancy between the bar chart and the pert data.
As are extrimated once for ever, or until next scheduling.
I used a 7 working days calendar.
Try to see which info are you asking to be shown in pert view.
If You want a copy of this and see how is running on your P3 send me You email.
Member for
22 years 3 monthsRE: Bar Chart & Network (PERT) Finish Dates not Ma
Did You try to re-set the activity box info in PERT view?
Member for
21 years 10 monthsRE: Bar Chart & Network (PERT) Finish Dates not Ma
To clarify my point, herebelow is a simple example.
Create a new project with planning unit in weeks, starting on mondays and with a start date of January 5th 2004.
Activity 1 has duration of 2 weeks and is linked with FS to Activity 2 that has a duration of 3 weeks.
The Bar Chart Layout shows Activity 1 finishing on January 18th 2004, and Activity 2 on February 8th, 2004, and both are correct.
Now, if you go to View, PERT, it shows Activity 1 finishing on January 12th 2004, and Activity 2 on February 2nd, 2004, and both are wrong. These 2 finish dates represent the starting dates of the weeks in which these activities end.
Hope my example is clear.
Anybody has an idea what is happening?
Thanks.
Member for
23 years 8 monthsRE: Bar Chart & Network (PERT) Finish Dates not Ma
please check the start day of the week are same. Project property and report option.