Ok, but I suppose the original question is how to hold or how to make the activities in the target project to stay in place (original position), even when moving the data date line (i mean in the Target Schedule itself).
regards
Member for
20 years 8 months
Member for20 years8 months
Submitted by Bijaya Bajracharya on Mon, 2007-04-23 06:08
I am not convinced as well. The best way is to keep the Target Programme untouched. Always work in your current programme only. To safeguard your target programme, you may even make it read only so that even if you open it, no change will be saved.
if youre not convinced, do you know any other solution? i mean im open. Target Projects (in real life Planning) once set is seldom changed. It takes a lot of arguments before anyone can get approval of a new Target Project!
are you Planning in real life Mark?
Member for
19 years 5 months
Member for19 years5 months
Submitted by Mark Chapman on Tue, 2007-04-17 10:28
I am not convinced you understand what Bijaya was saying. Any other version of your plan can become a target. If defined as a target then a schedule in the main plan wont move the dates in the target. Of course if you are in your target then a schedule can but defining extra constraints to your target is not the best solution.
never mind the place Bijaya, the issue is more important. Are you convince now that you need constraints in order for your Target activities not to move?
Member for
20 years 8 months
Member for20 years8 months
Submitted by Bijaya Bajracharya on Tue, 2007-04-17 09:12
You got the wrong spelling (ANOON), I know theres another one with that name (just copied it actually). Anyway, you might be right, but to make your Target Program immovable, I think thats the solution. And you can do whatever you want with it without affecting the early dates that you had set. You can estimate progress as you had planned it, in any date that you want and compare it with your current schedule or your actual one.
regards
Member for
20 years 8 months
Member for20 years8 months
Submitted by Bijaya Bajracharya on Sun, 2007-04-15 16:44
I think you are complicating things. Normally since you dont need to touch the target programme, you dont need to constraint any programme in the target programme. When you schedule your current programme, only the dates in the current programme change/move to new data date.
the solution is simple, put constraints on all of the activities of your Target schedule, you can do whatever you want with the data date, but the activities will surely not move (remember, constraints on your Target Schedule only)!
check the position of your current bar and your target bar (make sure you did not use the same position).
Member for
20 years 8 months
Member for20 years8 months
Submitted by Bijaya Bajracharya on Thu, 2007-04-12 11:00
It would have been good to continue the same thread for the problem instead of starting a new one.
Anyway back to your problem. There are certain circumstances when you will not see a target bar. One such situation is when you have added new activity in your current programme. Check if you have added any new programme.
One easy "method of detailing when an activity has not been progressed on the date that it was scheduled to" is to show Variance 1 (Target Early Start - Current Early Start). If the activities started as per target this value will be zero. If it has not started, it will start getting negative.
You can show Variance in column and even filter to show activities with negative variance.
Member for
20 years 8 monthsRE: activities moving with data date line - cont
Yes,
And Target activities will stay in the same position without doing anything. You see the most useful things in life comes FREE.
Member for
19 years 1 monthRE: activities moving with data date line - cont
Bijaya,
Ok, but I suppose the original question is how to hold or how to make the activities in the target project to stay in place (original position), even when moving the data date line (i mean in the Target Schedule itself).
regards
Member for
20 years 8 monthsRE: activities moving with data date line - cont
Anoon,
I am not convinced as well. The best way is to keep the Target Programme untouched. Always work in your current programme only. To safeguard your target programme, you may even make it read only so that even if you open it, no change will be saved.
Member for
19 years 1 monthRE: activities moving with data date line - cont
Mark,
if youre not convinced, do you know any other solution? i mean im open. Target Projects (in real life Planning) once set is seldom changed. It takes a lot of arguments before anyone can get approval of a new Target Project!
are you Planning in real life Mark?
Member for
19 years 5 monthsRE: activities moving with data date line - cont
Anoon,
I am not convinced you understand what Bijaya was saying. Any other version of your plan can become a target. If defined as a target then a schedule in the main plan wont move the dates in the target. Of course if you are in your target then a schedule can but defining extra constraints to your target is not the best solution.
Mark
Member for
19 years 1 monthRE: activities moving with data date line - cont
never mind the place Bijaya, the issue is more important. Are you convince now that you need constraints in order for your Target activities not to move?
Member for
20 years 8 monthsRE: activities moving with data date line - cont
I will remember now - Anoon. By the way, are you really in the Antarctica?
Member for
19 years 1 monthRE: activities moving with data date line - cont
Bijaya,
You got the wrong spelling (ANOON), I know theres another one with that name (just copied it actually). Anyway, you might be right, but to make your Target Program immovable, I think thats the solution. And you can do whatever you want with it without affecting the early dates that you had set. You can estimate progress as you had planned it, in any date that you want and compare it with your current schedule or your actual one.
regards
Member for
20 years 8 monthsRE: activities moving with data date line - cont
Annon,
I think you are complicating things. Normally since you dont need to touch the target programme, you dont need to constraint any programme in the target programme. When you schedule your current programme, only the dates in the current programme change/move to new data date.
Member for
19 years 1 monthRE: activities moving with data date line - cont
the solution is simple, put constraints on all of the activities of your Target schedule, you can do whatever you want with the data date, but the activities will surely not move (remember, constraints on your Target Schedule only)!
check the position of your current bar and your target bar (make sure you did not use the same position).
Member for
20 years 8 monthsRE: activities moving with data date line - cont
It would have been good to continue the same thread for the problem instead of starting a new one.
Anyway back to your problem. There are certain circumstances when you will not see a target bar. One such situation is when you have added new activity in your current programme. Check if you have added any new programme.
One easy "method of detailing when an activity has not been progressed on the date that it was scheduled to" is to show Variance 1 (Target Early Start - Current Early Start). If the activities started as per target this value will be zero. If it has not started, it will start getting negative.
You can show Variance in column and even filter to show activities with negative variance.