Microsoft Project Member for 20 years 6 months Member for 20 years 7 months Submitted by Zhang Haixiang on Tue, 2007-04-10 22:30 Permalink RE: MS-Project export to Excel of timephased data Hello, you can try the great method of copy and paste. Change the view to "task usage"/"resource usage"( Im not sure of the name, im using a chinese version), then copy the left part - task information to excel, then the right part the cost informaiton. hope this helps Log in or register to post comments
Member for 20 years 6 months Member for 20 years 7 months Submitted by Zhang Haixiang on Tue, 2007-04-10 22:30 Permalink RE: MS-Project export to Excel of timephased data Hello, you can try the great method of copy and paste. Change the view to "task usage"/"resource usage"( Im not sure of the name, im using a chinese version), then copy the left part - task information to excel, then the right part the cost informaiton. hope this helps
Member for
20 years 6 monthsRE: MS-Project export to Excel of timephased data
Hello,
you can try the great method of copy and paste.
Change the view to "task usage"/"resource usage"( Im not sure of the name, im using a chinese version), then copy the left part - task information to excel, then the right part the cost informaiton.
hope this helps