MS-Project export to Excel of timephased data

Member for

20 years 6 months

Hello,



you can try the great method of copy and paste.



Change the view to "task usage"/"resource usage"( I’m not sure of the name, i’m using a chinese version), then copy the left part - task information to excel, then the right part the cost informaiton.



hope this helps