Primavera Project Planner - P3 Member for 18 years 9 months Member for 18 years 9 months Submitted by Jonathan Ward on Tue, 2007-04-10 11:45 Permalink RE: cascade of activities without logic once again thank you for your kind help best regards jon Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Tue, 2007-04-10 11:20 Permalink RE: cascade of activities without logic Hi Jon, Yes you can organize and sort them by early start date. Goto Format-> Organize... on your P3 menu On Sort By box click Activity Id and change it to Early Start then Click Organize Now. You can add as many sorting your require. Rodel Log in or register to post comments
Member for 18 years 9 months Member for 18 years 9 months Submitted by Jonathan Ward on Tue, 2007-04-10 11:45 Permalink RE: cascade of activities without logic once again thank you for your kind help best regards jon
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Tue, 2007-04-10 11:20 Permalink RE: cascade of activities without logic Hi Jon, Yes you can organize and sort them by early start date. Goto Format-> Organize... on your P3 menu On Sort By box click Activity Id and change it to Early Start then Click Organize Now. You can add as many sorting your require. Rodel
Member for
18 years 9 monthsRE: cascade of activities without logic
once again
thank you for your kind help
best regards
jon
Member for
19 yearsRE: cascade of activities without logic
Hi Jon,
Yes you can organize and sort them by early start date.
Goto Format-> Organize... on your P3 menu
On Sort By box click Activity Id and change it to Early Start then Click Organize Now.
You can add as many sorting your require.
Rodel