Resource Limits & Leveling

Member for

20 years 6 months

For resource levelling there is no need to



1. Make the resources ’Driving’

2. No need for making the activities independent or meeting.



The above functions are only needed when we want the reosurces to use their own specific calenders and want the ’crunching and stretching’ of the activties.



The only thing which you would be missing is to include the resources in the levelling dialog box.



Rashid








Member for

22 years 9 months

Hi all,

do not forget to select the resources you want to level in the Level, Resources dialog

if you do not know WHICH resource is overloaded, select ALL resources

P3 will not level resources not selected here

Good luck,

Alexandre

Member for

22 years 1 month

There are few things you need to do for P3 to reschedule for a future date, an activity whose resource is not immediately available.



In addition to defining the resource limits and designating the resource as driving, you also need to select independent or meeting as the activity type. These selections will make P3 to recognize that the resource Calendar should be used in scheduling the activity and not the base calendar.



You also need to define the resource availability using the resource calendar (go to ‘Data’>> ‘Resources’ >> ‘Calendars’).



In leveling, P3 uses the combination of all these parameter to reschedule an activity whose resource is not available.



In summary try these steps:

1. Define the resource and resource availability using the resource calendar (go to ‘Data’>> ‘Resources’ >> ‘Calendars’).

2. Defining the resource limits

3. Designating the resource as driving

4. Choose independent or meeting as the activity type (if you select task as activity type, the base calendar will be used when leveling)



I am optimistic it would work.



Akin Adurosakin

Nigeria

Member for

19 years 5 months

Fro memory as I don’t use Resources that often, I think you have to define the resource as a driving resource. Is this the case?