Milestone Trend Analysis

Member for

24 years 9 months

Steve,

Spider Project keeps project archives (project history) and shows trends in time for any project parameter.

Our users can open project model as it existed at any moment in the past.

Actually we always suggest to manage by trends and discovering negative trends to find the reason. It is very useful for project performance analysis.

In project performance analysis we pay more attention to risk analysis (success probability trends).

Member for

24 years 9 months

Bilal,

I don’t know what you call milestone trend analysis but I can suggest what we use as trend analysis for milestones.

It is supported by Spider Project but can be done manually too.

Let t0 be the initial milestone finish date. After enetering 1st actual data it will become t1, 2nd - t2, etc. Now you can keep the history (for an example entering data in Excel) and create the graph that shows how forecasted finish date changed in time. If it rose you shall consider corrective action.

Another interesting trend - the variance from the baseline scheduled dates.

Trends can be created for cost and other data.

Member for

19 years 1 month

CPI, SPI, a lot of iss, EV, VE, VA, VM, a lot ess & mss, but none of them is a deliverable

Member for

20 years 7 months

My guess would be CPI and SPI earned value analysis. At least, that (in its different flavours) is one pretty good form of milestone trend analysis.

Member for

19 years 1 month

i guess it’s a series of deliverables depending on how you define it!