Progressing without Updating

Member for

19 years 1 month

Mathew,



Run the "update progress" under tools menu, enter the desired date when prompted and then click run.

Hope this helps.



BEN

Member for

19 years

Hi Mathew,



I think you’re referring to Progress Spotlight where you can update your progress against you data date. Any activities highlighted by progress spotlight will be updated automatically without extending dates.



HTH

Rodel

Member for

19 years 7 months

Hi Matthew,



U can use the "Schedule % complete" to show how much of the activity’s baseline duration has been completed so far (till the data date).



U can make a copy of the schedule that u work on and assign a baseline to it, then update the schedule as per ur data date and u’ll find the "Schedule % complete".



HTH.



Regards,

Karim