Primavera Project Planner - P3 Member for 14 years 2 months Member for 14 years 3 months Submitted by mdlepage on Tue, 2015-04-14 20:16 Permalink In case you're interested, In case you're interested, there's a detailed tutorial on building lookahead filters in Oracle Primavera here: https://www.planacademy.com/interactive-how-to-build-lookahead-filters-in-oracle-primavera-using-date-variables/ Regards, m Member for 18 years 9 months Member for 18 years 9 months Submitted by Ife Olyke on Sat, 2007-02-24 07:20 Permalink RE: 3 Days Lookahead Thanks Alexandre Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2007-02-23 05:20 Permalink RE: 3 Days Lookahead Hello, look at the Six-Month Lookahead filter, you should write: Early dates WR DD - DD+3D; be careful to have some tasks satisfying the filter calculation when you test it, to avoid an error message. Regards, Alexandre Log in or register to post comments
Member for 14 years 2 months Member for 14 years 3 months Submitted by mdlepage on Tue, 2015-04-14 20:16 Permalink In case you're interested, In case you're interested, there's a detailed tutorial on building lookahead filters in Oracle Primavera here: https://www.planacademy.com/interactive-how-to-build-lookahead-filters-in-oracle-primavera-using-date-variables/ Regards, m
Member for 18 years 9 months Member for 18 years 9 months Submitted by Ife Olyke on Sat, 2007-02-24 07:20 Permalink RE: 3 Days Lookahead Thanks Alexandre
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2007-02-23 05:20 Permalink RE: 3 Days Lookahead Hello, look at the Six-Month Lookahead filter, you should write: Early dates WR DD - DD+3D; be careful to have some tasks satisfying the filter calculation when you test it, to avoid an error message. Regards, Alexandre
Member for
14 years 2 monthsIn case you're interested,
In case you're interested, there's a detailed tutorial on building lookahead filters in Oracle Primavera here:
https://www.planacademy.com/interactive-how-to-build-lookahead-filters-in-oracle-primavera-using-date-variables/
Regards,
m
Member for
18 years 9 monthsRE: 3 Days Lookahead
Thanks Alexandre
Member for
22 years 9 monthsRE: 3 Days Lookahead
Hello,
look at the Six-Month Lookahead filter, you should write:
Early dates WR DD - DD+3D;
be careful to have some tasks satisfying the filter calculation when you test it, to avoid an error message.
Regards,
Alexandre