MPP to P3 (advanced)

Member for

22 years 9 months

Gün

Could be something like that; the project calendar in MSP is 8-12, 14-18, working 5 days a week, just the same as in P3

Alexandre

Member for

20 years 7 months

could be something related to MPP using each start hour of Day and P3 using start hour of day to end hour of day.



like a difference of 1 day is for mpp 24 hours. 7am to 7am.

for P3 its 7am to 5pm



sorry for this quick response, no time now.



Gün.