Primavera Project Planner - P3 Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2007-02-10 11:23 Permalink RE: MPP to P3 (advanced) Gün Could be something like that; the project calendar in MSP is 8-12, 14-18, working 5 days a week, just the same as in P3 Alexandre Member for 20 years 7 months Member for 20 years 7 months Submitted by Gün Göksu on Sat, 2007-02-10 11:12 Permalink RE: MPP to P3 (advanced) could be something related to MPP using each start hour of Day and P3 using start hour of day to end hour of day. like a difference of 1 day is for mpp 24 hours. 7am to 7am. for P3 its 7am to 5pm sorry for this quick response, no time now. Gün. Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2007-02-10 11:23 Permalink RE: MPP to P3 (advanced) Gün Could be something like that; the project calendar in MSP is 8-12, 14-18, working 5 days a week, just the same as in P3 Alexandre
Member for 20 years 7 months Member for 20 years 7 months Submitted by Gün Göksu on Sat, 2007-02-10 11:12 Permalink RE: MPP to P3 (advanced) could be something related to MPP using each start hour of Day and P3 using start hour of day to end hour of day. like a difference of 1 day is for mpp 24 hours. 7am to 7am. for P3 its 7am to 5pm sorry for this quick response, no time now. Gün.
Member for
22 years 9 monthsRE: MPP to P3 (advanced)
Gün
Could be something like that; the project calendar in MSP is 8-12, 14-18, working 5 days a week, just the same as in P3
Alexandre
Member for
20 years 7 monthsRE: MPP to P3 (advanced)
could be something related to MPP using each start hour of Day and P3 using start hour of day to end hour of day.
like a difference of 1 day is for mpp 24 hours. 7am to 7am.
for P3 its 7am to 5pm
sorry for this quick response, no time now.
Gün.