negative milestone

Member for

20 years

Total float is calculated from the end to begin of project. It means that if it delay 1 day, the project will delay 1 day. That is why it is still zero.



Regards.

Member for

19 years 3 months

I agree wirh brennan!! better u find a job!!..



The reason being the predecessor not finihsed as per planned and pushed the successor activity one month(in ur monthly update) and consumes the float.. simple my dear!! plz study closly the links !!



Thanks

Member for

22 years 8 months

Its difficult to answer without knowing the details of your schedule.



I assume it is the same schedule with a floating end date (ie not late constrained), I also assume that some progress was made on your critical path during the month. (if not then best to look for another job ;))



therefore the amount of progress made on your critical path will be equal to the reduction in float on the non critical activity you mentioned.

Member for

21 years 10 months

Thanks Brennan, but why for activity has positive total float, and no progress occurs, the total float decreases by approximately one month (updated monthly).



Regards,



Moutaz

Member for

22 years 8 months

The milestone is still on the critical path because its float equals zero, or its early finish is the same as its late finish.



Negative float occurs when your early finish is after your late finish. To fix the project end date and display variance in terms of float (negative float for over schedule) then apply a late finish constraint to your last activity.

Member for

20 years 3 months

Hi Moutaz,



you can ask Atef..





cheers