Dear Joe,



P3 can provide u a successor report by:

- Tool, project utilities,export

- choose EX-12, modify per ur requirement

above is effective only if u have maintained a good

records/corrections which are reflected in the as-built planned. otherwise it will not be of help, it can be done but it will be tedious process.



Hope this can assist u





G. Rayco

Member for

23 years 8 months

In P3, the linkages of a activity are maintained and not deleted even it is completed.

Prepare a prec and succ text report or Export the succ report will have the data