P3e calendar and timescale help

Member for

23 years 11 months

Try creating a new calendar for the non work periods and attaching the calendar to the activity.



Regards



Dave

Member for

22 years 8 months

hi



You can add a curtin window to display the non working period



HTH



ALex

Member for

22 years 3 months

Adele



What happens if you tick the box for ’Activity nonwork intervals’ rather than ’Calendar nonwork time’? Does this not give you what you need?



KB