Oracle Primavera - PM6 Member for 18 years 10 months Member for 18 years 10 months Submitted by Bilal Mohammed on Sun, 2007-01-07 04:23 Permalink RE: Primavera P 5.0 schedule problem Hi mktse Thanx for ur reply. But for the solution, if i give start and finish for ES & EF, then the columns will be updated with actual start and actual finish Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2007-01-07 04:07 Permalink RE: Primavera P 5.0 schedule problem Your post is better on forum "Primavera Enterprise - Teamplay / P3e & P3ec" since P5.0 is under that category. Anyway, select the field "Start" and "Finish" rather ES/EF Log in or register to post comments
Member for 18 years 10 months Member for 18 years 10 months Submitted by Bilal Mohammed on Sun, 2007-01-07 04:23 Permalink RE: Primavera P 5.0 schedule problem Hi mktse Thanx for ur reply. But for the solution, if i give start and finish for ES & EF, then the columns will be updated with actual start and actual finish
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2007-01-07 04:07 Permalink RE: Primavera P 5.0 schedule problem Your post is better on forum "Primavera Enterprise - Teamplay / P3e & P3ec" since P5.0 is under that category. Anyway, select the field "Start" and "Finish" rather ES/EF
Member for
18 years 10 monthsRE: Primavera P 5.0 schedule problem
Hi mktse
Thanx for ur reply. But for the solution, if i give start and finish for ES & EF, then the columns will be updated with actual start and actual finish
Member for
23 years 8 monthsRE: Primavera P 5.0 schedule problem
Your post is better on forum "Primavera Enterprise - Teamplay / P3e & P3ec" since P5.0 is under that category.
Anyway, select the field "Start" and "Finish" rather ES/EF