Project 2007 changes my 2003 durations??

Member for

19 years

MS have added a new resource type ’cost’ this appears to give the same affect as my work around. You create the task with a pounds cost in the cost column and duration and then assign the supplier (who you have set as a ’cost’ type resource) to the task and it automatically set the works hours to 0 (it even locks you out of the work column). Good Stuff!!!