P3 calculates % complete by calculating the percentage of actual duration wrt Total duration. i.e (OD-RD)/OD
However, if you dont want to use this rule, you can remove the linkage by Autocost rule, But in that case you have to feed % completion and Remaining Duration manually.
Yes, we can set % completion for summerized activity (Tool >Option>summerization)in three way i.e. by Duration, Resources unit and cost.
and even you can set different method for different section if you are using more than one calander in your project.
Thanks
Prabin Kumar
Member for
22 years 2 months
Member for22 years3 months
Submitted by Ronaldo Quilao on Tue, 2006-12-12 09:24
Member for
22 years 8 monthsRE: How P3 is calculating % complete.....
hi ronald how are you nice to hear from you.......
i have done that already what all of you have mentioned
i even ask some planners here also.....
let me rephrase my question......
if i will summarize all the activities the % complete lets say 67% complete
if i would schedule the programme it will show 57% why there is a difference.......i keep on encountering this problem
do i have to ask my boss to renew the license??? do i have to replace my PC??? :)
follow up question......
lets say i have a delay of 8% on the over all programme i would like to know what % of the overall delays is the blockworks alone????
tnx in advance guys :)
Member for
20 years 1 monthRE: How P3 is calculating % complete.....
Hi Ray,
P3 calculates % complete by calculating the percentage of actual duration wrt Total duration. i.e (OD-RD)/OD
However, if you dont want to use this rule, you can remove the linkage by Autocost rule, But in that case you have to feed % completion and Remaining Duration manually.
Yes, we can set % completion for summerized activity (Tool >Option>summerization)in three way i.e. by Duration, Resources unit and cost.
and even you can set different method for different section if you are using more than one calander in your project.
Thanks
Prabin Kumar
Member for
22 years 2 monthsRE: How P3 is calculating % complete.....
Dear Rey,
How you doing?
Try to check AutoCost Rule. You can click whichever fit to your requirements in calculation.
Regards,
Ronald
Member for
23 years 8 monthsRE: How P3 is calculating % complete.....
When do summary, summarized PCT=
[(SumOfOD - SumOfRD)/SumOfOD]x100%
Member for
23 years 8 monthsRE: How P3 is calculating % complete.....
According to P3 manual, PCT is "The proportion of an activity that has been completed".
PCT=[(OD-RD)/OD]x100%