I agree to both solutions... either global change or exporting it to excel will do... just choose which one you are more comfortable/confident using...
for me, i will enter the resource and curve type in one activity. then export this activity to WK1 (selecting fields Act ID, Des, OD, RES, Units, etc.)
Then in open up this WK1 file in excel, eneter the Act ID for the activities i want to assign with this resource.
copy paste the resource data to these other activities, modify the units per day (or budget qty) as necessary.
Finally import this file back in to P3.
Voila! Done...
Member for
19 years
Member for19 years
Submitted by Tahir Naseem P… on Mon, 2006-11-27 18:47
Member for
22 years 5 monthsRE: multiple resource assignmnet
I agree to both solutions... either global change or exporting it to excel will do... just choose which one you are more comfortable/confident using...
good luck!
Member for
19 yearsRE: multiple resource assignmnet
for me, i will enter the resource and curve type in one activity. then export this activity to WK1 (selecting fields Act ID, Des, OD, RES, Units, etc.)
Then in open up this WK1 file in excel, eneter the Act ID for the activities i want to assign with this resource.
copy paste the resource data to these other activities, modify the units per day (or budget qty) as necessary.
Finally import this file back in to P3.
Voila! Done...
Member for
19 yearsRE: multiple resource assignmnet
Dear
The same simple solution
global change you can assign the curve type with the same methode.
Member for
19 years 2 monthsRE: multiple resource assignmnet
Well Christian
i have added the resource to the activites but what about the curve, units per day ?
soory but i need this too
thanx
sami
Member for
19 years 2 monthsRE: multiple resource assignmnet
thanks Christian
i mworking on that now
i tell you if any probs came up
sami
Member for
22 years 5 monthsRE: multiple resource assignmnet
Sami
the global change is a helpful feature....
hth
Christian