multiple resource assignmnet

Member for

22 years 5 months

I agree to both solutions... either global change or exporting it to excel will do... just choose which one you are more comfortable/confident using...



good luck!

Member for

19 years

for me, i will enter the resource and curve type in one activity. then export this activity to WK1 (selecting fields Act ID, Des, OD, RES, Units, etc.)

Then in open up this WK1 file in excel, eneter the Act ID for the activities i want to assign with this resource.

copy paste the resource data to these other activities, modify the units per day (or budget qty) as necessary.

Finally import this file back in to P3.

Voila! Done...

Member for

19 years

Dear

The same simple solution

global change you can assign the curve type with the same methode.

Member for

19 years 2 months

Well Christian







i have added the resource to the activites but what about the curve, units per day ?



soory but i need this too





thanx



sami

Member for

19 years 2 months

thanks Christian



i mworking on that now



i tell you if any probs came up





sami

Member for

22 years 5 months

Sami



the global change is a helpful feature....



hth



Christian