Rolling up tasks to a summary task

Member for

19 years 11 months

James



Yes - you do make sense. I only use the rolled up effect on each package, not on an "overall summary" as that would be very busy. Each package is made up of end to end activitites, so that when I roll them up they work very well. I then have to double click on each segment of the rolled up summary bar to create a shape and colour which will represent each activity. When the bar is complete the activities are all on the one bar looks great. What I was really asking was, is there a way of creating the shapes and colours within the summary bar easily, after I have produced the programme without having to double click on each activity - say each package has 15 activities, and there were 50 packages - thats a lot of double clicking !!!. I can create a flag format for normal activities, so that if I tick the flag1 box every activity under that flag will be a certain colour and shape, however the summary bar does not reflect the format. As I said earlier I have created one package and copied it many times. This works well and I change each package as is needed . The problem has come to my attention as one of my colleagues has created a design programme on similar lines but had not formatted the summary bars before copying, and now wants to summarise the design elements into a smaller programme.

Member for

19 years 5 months

Andrew,



Dunno if it’s quite what you’re looking for – but on the overall summary bar, the one that all the packages are rolled-up to, you can hide specific portions of it. However, the messiness of the overall summary bar is dependent on how many sub-packages you have relative to it and running in parallel.



Essentially, within each sub-package, I’ve defined a few tasks and a few milestones. As you create each package, click the overall summary-bar “+” and the sub-package tasks roll-up into the summary-bar. Double-click on the overall rolled-up bar and you should get the window that allows you to define the shape and colour of the rolled-up bar. You then change the SHAPE to show a blank, for the long tasks but you leave the milestone portion of the bar. The result is that you can show just the milestones for each of the sub-packages.



Each time you add a new package you will have to go through the same process of making the rolled-up summary bar disappear because, when rolling-up, it overlays all of the rolled-up tasks on top of each other.



Does this make any sense?



James.

Member for

19 years 11 months

Alexandre



That VBA thing again !!. I guess that I am going to have to learn how to use VBA. Anybody got some good advice where I start ?



Regards



Andrew

Member for

19 years 5 months

Andrew,



On the overall summary-bar, have you tried hiding it - or turning it into a transparent bar?



James.

Member for

22 years 9 months

Andrew,

you are asking too much!

maybe a few lines of VBA would help?

Alexandre