Calculating % Complete, OD & RD

Member for

19 years

Hi guys cheers for the advice. i did have my data data set as the current date, the problem being was i wasn’t updating progress correctly. for activities that have started i now put an expected finish constraint on and this then calculates my % complete. This then calculated my rd as long as the od is correct.

thanks again it’s all a learning curve...

Member for

18 years 11 months

Mark,



My understanding about your query is that if you have Kept auto cost rulle ON so that percentage progress can be linked to remaining duration, than the remaining duration will be calculated based on percentage completion and vice versa.In such case ur RD will be based on actual duration required as your activity is already started.



I hope my understanding is correct.As I am now at such location, where I am not having Primavera on my system for time being, I have not validated my reply, so if anybody have better solution please provide, which will be appreciated.



Regards



Umerfarook Deshmukh