Sorry but I do not know what BOQ stands for but what may help is by default Primavera projects are setup using Duration as the Percent Complete Type. If you are updating percentages on duration based progress and want the Earned value to be calculated from this percentage then on the Project screen select the Calculations tab and tick "Recalculate Actual Units and Cost when duration % complete changes".
Or try the following might also help
To calculate activity, resource, and expense actuals according to the project plan, rather than hours, units, and completion percentages reported by resources, mark the Auto Compute Actuals checkbox for each resource (in the Details tab of Resource Details) or nonresource cost (in the Expenses tab of Activity Details).
Member for
22 years 8 monthsRE: BOQ in P3 ec
angyan
To load the BOQ you can
First set up the CBS activity From the contract items breakdown CBS - Cost Breakdown Strcuture
Then load the CBS activities with the resource unit and cost from your BOQ.
Then breakdown the WBS in accordance with the actual works that need to be preform. (Sometime CBS is not always WBS)
Once this is done, then you update the WBS each month and using the EV from the WBS and update the CBS activities that loaded with the BOQ
Never use auto-complete if you relate your earn vaule with your BOQ
Good Luck
Alex
Member for
19 years 4 monthsRE: BOQ in P3 ec
Thanks,
Please note that BOQ means Bill of Quanitities and in any contract we do have the value of the contract broken down into items of the BOQ.
Regards
angyan
Member for
19 years 6 monthsRE: BOQ in P3 ec
Sorry but I do not know what BOQ stands for but what may help is by default Primavera projects are setup using Duration as the Percent Complete Type. If you are updating percentages on duration based progress and want the Earned value to be calculated from this percentage then on the Project screen select the Calculations tab and tick "Recalculate Actual Units and Cost when duration % complete changes".
Or try the following might also help
To calculate activity, resource, and expense actuals according to the project plan, rather than hours, units, and completion percentages reported by resources, mark the Auto Compute Actuals checkbox for each resource (in the Details tab of Resource Details) or nonresource cost (in the Expenses tab of Activity Details).
Cheers