problem with as late as possible constraint

Member for

11 years 6 months

Hi,

By giving Priority to that task you can avoid the duration problems

Member for

20 years 3 months

i’ve send the sample project to your mails. I wrote some about project but If you need further explanation please tell me.

Member for

20 years 3 months

First thanks for dealing with my problem I’m working with MS Project 2003. I tried everything but I couldn’t solve the problem and I know that its unsolvable with MS Project (without extra software)its easily seen that MS Project is deficient in leveling but its available solving the problem with critical chain consepts so i used prochain as an extra software for MS Project. I’ll send you the project as soon as possible thanks again.


Member for

22 years 9 months

Ersin,

which version of MS Project are you using?

Have you set up the project START date or FINISH date (Project, Project Information)?

Task default constraint is ASAP for a project set forward, ALAP for project set backward

MS Project is not too good at leveling resources in a backward project. I had the experience where a backward project was leveled toward the end of the project instead of the beginning.

Send your file to afaulxbriole@wanadoo.fr if you want.

Regards

Member for

19 years 7 months

I’m not so good at this levelling thingy...



- HAve you set "deadline"?

- Maybe the setting for each activity?



Need to test to check the reasons via the file...