Pharma Project - Validation

Member for

18 years 11 months

Davide/ Peter



Can anyone of u email me P3 schedule for any Pharma Project. I will be thanksful to you.



my emailid is umerfarooque@yahoo.com



Regards



Umerfarook Deshmukh

Member for

20 years 5 months

Davide,



we tend to use modulat test scripts which cuts down on the total number of docs needed.



Weighting - I just use the estimate manhours for that V&Q phase with individual manhour activities prorata to their durations, as generally only 1 or 2 people produce the docs



100% Credit is only given at client doc sign off so set progress plan accordingly



Rgds



Peter

Member for

21 years 6 months

Peter,



I did a nice P3 network having all the link and all the right sequnce to manage and controll the V&Q schedule.

I have more difficulties to manage the progress of the protocols or report, to track them and to link them to the related P3 activities (for each level 3 activities we can have to 6 IQ/QO protocols and report).



How do you weight the protocols ? Point, Stdmhrs, nr. of page ?



Thanks



Davide

Member for

20 years 5 months

Davide ,



can you be more specific ?



Here the V & Q work is scheduled as part of the project work in the normal manner from DQ, IQ, OQ & PQ.

The department gets it own level 3 programme and then generally uses excel / access to create the lists / matrices required for tracking creation, approval and registering of all those documents specified in the master plan.