Primavera Project Planner - P3 Member for 23 years 6 months Member for 23 years 6 months Submitted by Vincent Tham on Fri, 2003-11-07 14:12 Permalink RE: Discrepancy on % completed & Total Float By solved this problems, i recommended you to execute "re-organize now" command 2 times before every time when you want to explain. sure it will solve your problems. Sure you have any prolems,you can direct contact me. 012-2867713. Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Tue, 2003-10-21 13:47 Permalink RE: Discrepancy on % completed & Total Float Both PCT and TF of summary bar are determined by various factors which can be control in Option - summarization. However, settings may be overrided by parameter in each report template. Please check. Further, to reduce the changing of these 2 value on screen during editing, stop the auto-scheduling function, hope help. Log in or register to post comments
Member for 23 years 6 months Member for 23 years 6 months Submitted by Vincent Tham on Fri, 2003-11-07 14:12 Permalink RE: Discrepancy on % completed & Total Float By solved this problems, i recommended you to execute "re-organize now" command 2 times before every time when you want to explain. sure it will solve your problems. Sure you have any prolems,you can direct contact me. 012-2867713.
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Tue, 2003-10-21 13:47 Permalink RE: Discrepancy on % completed & Total Float Both PCT and TF of summary bar are determined by various factors which can be control in Option - summarization. However, settings may be overrided by parameter in each report template. Please check. Further, to reduce the changing of these 2 value on screen during editing, stop the auto-scheduling function, hope help.
Member for
23 years 6 monthsRE: Discrepancy on % completed & Total Float
By solved this problems, i recommended you to execute "re-organize now" command 2 times before every time when you want to explain. sure it will solve your problems.
Sure you have any prolems,you can direct contact me. 012-2867713.
Member for
23 years 8 monthsRE: Discrepancy on % completed & Total Float
Both PCT and TF of summary bar are determined by various factors which can be control in Option - summarization.
However, settings may be overrided by parameter in each report template. Please check.
Further, to reduce the changing of these 2 value on screen during editing, stop the auto-scheduling function, hope help.