Mario,



Thanks for that, The one thing I was struggling to achieve was linking the first/last MSP activities into Primavera to see how it impacts in the overall programme. Are you suggesting this should be possible?



Paul

Member for

19 years 2 months

I’m cautious when moving a programme from MSP to P3e, it’s not always a smooth transition. MSP and P3e don’t always follow the same rules when it comes to things like constraints, calendar’s or resource assignments. The process I follow is to import MSP programmes into a standalone version of P3e where I can check it and fix any anomalies which have occurred during the import. Once it’s been cleaned it can go into the main database. It’s a little long winded but it saves you from having to deal with any surprises in your operating database.

Member for

22 years 7 months

To link P5 with MSP there is an application called projectlink, or something similar, that comes with the software.



HTH

Member for

19 years 3 months

I have used the option of saving the programme to Primavera when in MSP through the Primavera toolbar but this just gives read only access.