I got this from the primavera tech support that the GPF was due to the number of holidays in each calender had exceeded the limit of 935 days. Where as the change in remaining duration is a known problem in P5 which occurs on activites with remaining duration equal to 1. This would be taken care of in next release of p5
Member for
22 years 10 months
Member for22 years10 months
Submitted by Ronald Winter on Wed, 2006-09-06 10:23
One thing to be wary of is that P5 does not have the P3 Interruptible Activities CPM calculation setting. Be sure to use Continious Activities. Good luck!
Somewhere in the documentation there is a list of steps to take to reduce GPF errors. Sorry I cant remember where!
Go to Help About from the menu and check your version. It should show 3.1 SP3. If not SP3 then log on to the Primavera web site and download the Service Pack 3 update. These Service Packs are not on the installation disks. (This solved a repeated GPF on a new installation for us.)
Member for
19 years 4 months
Member for19 years4 months
Submitted by Abhijeet Ranadhir on Thu, 2006-08-31 12:46
I used a new built calender in P5 to ecport the schedule back to P3 and it worked. I have another probelem now. Duration on some of teh activities changes after I export and schedule from P5 to P3. Please let mw know If anyone has encounted with such a situation. It would be a great HELP.
Member for
19 years 4 months
Member for19 years4 months
Submitted by Abhijeet Ranadhir on Wed, 2006-08-30 11:08
What version of P3 are you running. When P3v2 16bit was recompiled to take advantage of Windows 32bit environment it was not fully NT compliant on version 3.0, thus 3.1 followed shortly to remidy this. NT does not allow applications to make direct calls to Periffials. So if you are running Windows NT,2000 or XP ensure you are running P3v3.1, other than this...?
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Wed, 2006-08-30 09:37
Member for
19 years 4 monthsRE: General protection Fault Error in P3.exe
I got this from the primavera tech support that the GPF was due to the number of holidays in each calender had exceeded the limit of 935 days. Where as the change in remaining duration is a known problem in P5 which occurs on activites with remaining duration equal to 1. This would be taken care of in next release of p5
Member for
22 years 10 monthsRE: General protection Fault Error in P3.exe
One thing to be wary of is that P5 does not have the P3 Interruptible Activities CPM calculation setting. Be sure to use Continious Activities. Good luck!
Member for
21 years 5 monthsRE: General protection Fault Error in P3.exe
Somewhere in the documentation there is a list of steps to take to reduce GPF errors. Sorry I cant remember where!
Go to Help About from the menu and check your version. It should show 3.1 SP3. If not SP3 then log on to the Primavera web site and download the Service Pack 3 update. These Service Packs are not on the installation disks. (This solved a repeated GPF on a new installation for us.)
Member for
19 years 4 monthsRE: General protection Fault Error in P3.exe
I used a new built calender in P5 to ecport the schedule back to P3 and it worked. I have another probelem now. Duration on some of teh activities changes after I export and schedule from P5 to P3. Please let mw know If anyone has encounted with such a situation. It would be a great HELP.
Member for
19 years 4 monthsRE: General protection Fault Error in P3.exe
Nigel, I am using Pv3.1.
Member for
19 years 6 monthsRE: General protection Fault Error in P3.exe
What version of P3 are you running. When P3v2 16bit was recompiled to take advantage of Windows 32bit environment it was not fully NT compliant on version 3.0, thus 3.1 followed shortly to remidy this. NT does not allow applications to make direct calls to Periffials. So if you are running Windows NT,2000 or XP ensure you are running P3v3.1, other than this...?
Member for
22 years 9 monthsRE: General protection Fault Error in P3.exe
In this case, I cannot answer
Member for
19 years 4 monthsRE: General protection Fault Error in P3.exe
I may try it. Thank You. FYI it gives the error only on the schedules which I export from P5.
Member for
22 years 9 monthsRE: General protection Fault Error in P3.exe
Hello,
I would uninstall then reinstall the software.
Regards