1. Use export and export all your successors using a dBASE III/IV format. This is to ensure your file is not truncated due to the old Lotus row restrictions.
2. Copy you subprojects out into the new master project and then import the file you exported previously.
3. If you change you project IDs you will have to edit the exported DBF file to change the Project ID code in the Activity ID, you can edit this file using Microsoft Excel.
hope this works for you or at least gives you a start in the right direction.
Member for
19 years 6 monthsRE: Creating/Merging and/or Copying subprojects
Alright this is not tooooo difficult.
1. Use export and export all your successors using a dBASE III/IV format. This is to ensure your file is not truncated due to the old Lotus row restrictions.
2. Copy you subprojects out into the new master project and then import the file you exported previously.
3. If you change you project IDs you will have to edit the exported DBF file to change the Project ID code in the Activity ID, you can edit this file using Microsoft Excel.
hope this works for you or at least gives you a start in the right direction.