Primavera Project Planner - P3 Member for 21 years 4 months Member for 21 years 4 months Submitted by Trevor Lyle on Thu, 2006-08-10 11:39 Permalink RE: P3 SCHEDULE VARIANCE Thanks William I am on vacation at present and will try your suggestion when I return to the office next week. Thanks again. Trevor Lyle Member for 19 years 9 months Member for 19 years 9 months Submitted by William Desamero on Wed, 2006-08-09 13:14 Permalink RE: P3 SCHEDULE VARIANCE Hi Trevor, To clear variances (per activity): 1. check that your remaining duration (RD) is not equal to 0 2. if RD is 0, reset your progress PCT % to 0 (note previous figure) 3. increase your original duration (OD) and enter orig PCT % 4. repeat items 1 & 2 until RD is at least 1 5. click Res (Resources) Tab 6. edit the figure "At Completion" and make it equal to "Budgetted Quantity" 7. Click OK. Hope this helps. William Log in or register to post comments
Member for 21 years 4 months Member for 21 years 4 months Submitted by Trevor Lyle on Thu, 2006-08-10 11:39 Permalink RE: P3 SCHEDULE VARIANCE Thanks William I am on vacation at present and will try your suggestion when I return to the office next week. Thanks again. Trevor Lyle
Member for 19 years 9 months Member for 19 years 9 months Submitted by William Desamero on Wed, 2006-08-09 13:14 Permalink RE: P3 SCHEDULE VARIANCE Hi Trevor, To clear variances (per activity): 1. check that your remaining duration (RD) is not equal to 0 2. if RD is 0, reset your progress PCT % to 0 (note previous figure) 3. increase your original duration (OD) and enter orig PCT % 4. repeat items 1 & 2 until RD is at least 1 5. click Res (Resources) Tab 6. edit the figure "At Completion" and make it equal to "Budgetted Quantity" 7. Click OK. Hope this helps. William
Member for
21 years 4 monthsRE: P3 SCHEDULE VARIANCE
Thanks William
I am on vacation at present and will try your suggestion when I return to the office next week.
Thanks again.
Trevor Lyle
Member for
19 years 9 monthsRE: P3 SCHEDULE VARIANCE
Hi Trevor,
To clear variances (per activity):
1. check that your remaining duration (RD) is not equal to 0
2. if RD is 0, reset your progress PCT % to 0 (note previous figure)
3. increase your original duration (OD) and enter orig PCT %
4. repeat items 1 & 2 until RD is at least 1
5. click Res (Resources) Tab
6. edit the figure "At Completion" and make it equal to "Budgetted Quantity"
7. Click OK.
Hope this helps.
William