Primavera Project Planner - P3 Member for 22 years 3 months Member for 22 years 4 months Submitted by Jorge Taguinod on Tue, 2003-10-07 02:47 Permalink RE: p3 / suretrack compatability Hi Martin! Sorry but some data fields in P3 cannot be read by SureTrak. These include custom data items, cost accounts, period performance, chaning unit prices of resources, etc. Best regards, Jorge Log in or register to post comments
Member for 22 years 3 months Member for 22 years 4 months Submitted by Jorge Taguinod on Tue, 2003-10-07 02:47 Permalink RE: p3 / suretrack compatability Hi Martin! Sorry but some data fields in P3 cannot be read by SureTrak. These include custom data items, cost accounts, period performance, chaning unit prices of resources, etc. Best regards, Jorge
Member for
22 years 3 monthsRE: p3 / suretrack compatability
Hi Martin!
Sorry but some data fields in P3 cannot be read by SureTrak. These include custom data items, cost accounts, period performance, chaning unit prices of resources, etc.
Best regards,
Jorge