Client scope works

Member for

19 years 3 months

Hello Andrew,



Thank you for the reply. Please find below the details.



According to approverd schedule, works proceed until the installation of Conveying System (Passenger lifts). In this time owner himself decided to change either the system or manufacturer (offcourse it is outside delivery). In this case, what would have be the sensible comments from his side?



Did he approve the time extentsion requested by contractor, according to material submittals and delivery confirmation?

Or he ask contractor to revise the schedule, from this activities and adjust the successor activities to incoperate the milestone dates of former schedule.


Member for

20 years 10 months

Giji,



On the face of what I think you are saying, yes, but alittle more detail would be helpful.