WBS Presentation

Member for

20 years 3 months

Hi,



The essential of WBS is very simple. WBS stand for WORK BREAKDOWN STRUCTURE. This is to break down the Scope of work from the highest level of detail to the lowest of detail.



If you are a planner with suficient years of contruction expereince it would be easy to visualize from the SOW which level constitute the higher level then the lowest level.



Cheers,



Charlie


Member for

20 years 5 months

PMI have issued industry applicable WBS templates. Have a look at their web site

Member for

19 years 5 months

Jerry,



In my environment, Nuclear Equipment Design, we tend to initially format the programme this way:



L1: Project title.

L2: Project Phase (Design, Manufacture, Installation, Commissioning).

L3: System Name (Work Package Name)eg. Crane, Shield Doors, Conveyors.

L4: Sub-system Name and their detailed activities.



Occasionally we go down to L8 or even 9, depending upon the complexity and how it needs to be reported. This is what I like about using MSP and the "Group By " function. It is extremely easy to format the program to whatever is desired.



As stated, there is no absolutely right way of formatting a programme. It will vary according to the environment and to whom you are reporting. The important thing is that you can extract the information.



As time goes-on, you’ll find the way that suits you.



James.

Member for

20 years 3 months

Jerry,



Your concept of WBS is correct though the level of details may vary on each project.



In the oil, gas and power plant projects where i’ve been involved in the past 12 yrs the level 2 details normally shows each area, level 3 by system and level 4 by discipline or main equipment. Find out which breakdown best suits your project and start from your ITB.



Nathaniel - Philippines