P3ec has two places where dates can go, early dates and planned dates. When you perform a CPM analysis, the calculations go into the early dates section. When you do a resource leveling, the new leveled dates go into the planned dates section. The leveled dates will also go into the early dates section unless you use the option that you asked about. Good luck!
Member for
19 years 8 months
Member for19 years8 months
Submitted by Michael Craig on Wed, 2006-07-26 16:51
Member for
22 years 10 monthsRE: Resource Leveling Need Help
P3ec has two places where dates can go, early dates and planned dates. When you perform a CPM analysis, the calculations go into the early dates section. When you do a resource leveling, the new leveled dates go into the planned dates section. The leveled dates will also go into the early dates section unless you use the option that you asked about. Good luck!
Member for
19 years 8 monthsRE: Resource Leveling Need Help
I should have clarified sorry Im talking about P3E 4.0
Thanks