Oracle Primavera - PM6 Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Mon, 2006-07-24 21:01 Permalink RE: Im porting mpx, mpp to P5 Just do a filter showing activity type = WBS summary and delete all. Regards. Member for 19 years 4 months Member for 19 years 5 months Submitted by Hady Shendy, PMP on Sun, 2006-07-23 11:02 Permalink RE: Im porting mpx, mpp to P5 Importing mpp to p5 when import mmp files to primavera p5, the summary tasks become activities plus its character as WBS level please advise to keep the summary tasks on MSP as a WBS level with imported into P5 Thanks Log in or register to post comments
Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Mon, 2006-07-24 21:01 Permalink RE: Im porting mpx, mpp to P5 Just do a filter showing activity type = WBS summary and delete all. Regards.
Member for 19 years 4 months Member for 19 years 5 months Submitted by Hady Shendy, PMP on Sun, 2006-07-23 11:02 Permalink RE: Im porting mpx, mpp to P5 Importing mpp to p5 when import mmp files to primavera p5, the summary tasks become activities plus its character as WBS level please advise to keep the summary tasks on MSP as a WBS level with imported into P5 Thanks
Member for
20 yearsRE: Im porting mpx, mpp to P5
Just do a filter showing activity type = WBS summary and delete all.
Regards.
Member for
19 years 4 monthsRE: Im porting mpx, mpp to P5
Importing mpp to p5
when import mmp files to primavera p5, the summary tasks become activities plus its character as WBS level
please advise to keep the summary tasks on MSP as a WBS level with imported into P5
Thanks