Creating a graphic reports in P3 v5

Member for

20 years

Activity usage profile or Assignements (in this option u have to copy and paste to excel)



Also look for ather threads about S-Curve.



Regards.

Member for

20 years

Hi



Not 100% sure what you want to do here but check out the activity usage profile and plot the EAC curve. This will give you a cost S-Curve which can be compared with the budget.



This S-curve will take into account the WBS settings for the WBS element the activities are in but if the EV settings are left as ETC = remaining cost for activity and the EV technique set as Activity percent complete then you will get an s-curve based on the activity percent complete with no no adjustment for CPI on the forecast





Peter