Not 100% sure what you want to do here but check out the activity usage profile and plot the EAC curve. This will give you a cost S-Curve which can be compared with the budget.
This S-curve will take into account the WBS settings for the WBS element the activities are in but if the EV settings are left as ETC = remaining cost for activity and the EV technique set as Activity percent complete then you will get an s-curve based on the activity percent complete with no no adjustment for CPI on the forecast
Member for
20 yearsRE: Creating a graphic reports in P3 v5
Activity usage profile or Assignements (in this option u have to copy and paste to excel)
Also look for ather threads about S-Curve.
Regards.
Member for
20 yearsRE: Creating a graphic reports in P3 v5
Hi
Not 100% sure what you want to do here but check out the activity usage profile and plot the EAC curve. This will give you a cost S-Curve which can be compared with the budget.
This S-curve will take into account the WBS settings for the WBS element the activities are in but if the EV settings are left as ETC = remaining cost for activity and the EV technique set as Activity percent complete then you will get an s-curve based on the activity percent complete with no no adjustment for CPI on the forecast
Peter
Member for
24 years 6 monthsRE: Creating a graphic reports in P3 v5
Andrew
www.DecisionEdge.com
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au