resource calendars

Member for

19 years 4 months

Paul,

Thanks for your kind help.

Member for

24 years 6 months

Question 1



Benny



Each resource may only have one calendar. For the resource to schedule with a calendar it must be Independent or Meeting Task Type.



Question 2

You may use Global change to change the quantity o resources. You need to understand the Autocost rules before you use this function.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au